Synopsis- The Pink Line of Namma Metro is India’s deepest underground line, and this hall of 21.25 km will cater to Bengaluru’s (Part II) most bold BMRCL challenge. The pink line is predicted to be launched in phases by late 2026 to enhance north-south connectivity, decongest roadways, multimodal integration and three–4 lakh ridership (doubtlessly).
The Namma Metro Part II challenge marks an excellent achievement in Bengaluru’s transport historical past. There’s 21.2 km of underground metro rail within the Pink Line – the deepest stretch of underground metro in India – serving essential healthcare, training, and enterprise neighbourhoods. The Pink Line will deal with transportation within the metropolis and accessibility by connecting the flavours of north and south Bengaluru, giving the lakhs of Bengalureans one other alternative to fantasise about their day by day commutes as soon as once more and relieve the transportation woes.
Route Particulars & Station Protection
- The Pink Line is 21.25 kilometres lengthy, one half consists of a 7.5-kilometre elevated part from Kalena Agrahara to Tavarekere, and one half consists of a 13.8-kilometre underground part from Dairy Circle to Nagawara (making it the longest underground stretch within the Namma Metro system).
- The Pink Line has 18 stations in whole, of which 6 are elevated and 12 underground, have been intentionally designed and deliberate to point out accessibility and connectivity into densely populated, residential, academic and industrial areas.
- Notable interchange stations:
- Jayadeva Hospital (connection to the Yellow Line)
- MG Highway (connection to the Purple Line)
- Nagawara (connection to the brand new Blue Line)
- Dairy Circle (proposed interchange station for the deliberate Purple Line)
- Key areas:
- Kalena Agrahara, JP Nagar, Dairy Circle, MG Highway, Shivajinagar, Bengaluru Cantonment, Tannery Highway, and Nagawara; offering extra last-mile connections and multimodal connectivity throughout town.
Development & Technical Highlights
- Underground Part – Engineering Problem: The alignment of Pink Line’s underground is 13.8 km in size, and it’s the longest and essentially the most technical part of the Namma Metro. This part is difficult as a consequence of heavy geological formations, similar to granite and dolerite, which affect the tunnelling course of. At this level, twin-bore tunnelling is lastly completed, and primarily based on civil building work, they’re at 90% completion as of mid-2025.
- Elevated Part – Job Completion: The elevated part of the Pink Line that runs from Kalena Agrahara to Tavarekere is full as an entire, and it’s simply ready for system-level testing and integration.
- Electrification – Energy Provide System: The Pink Line can be powered by a 750V DC third rail system akin to international requirements for metro methods, and it’ll even be in line with the prevailing electrification energy provide system of Namma Metro.
Security Trials & Regulatory Milestones
- Third Rail Energisation Trials Start
- In June 2025, BMRCL commenced third rail energisation on the elevated part from Jayadeva to Tavarekere, a serious step towards changing into operationally prepared.
- Full Scale Testing Underway
- Calibrating the signalling system
- Integrating the telecommunications gear
- Load of the observe and the buildings are being examined
- These security trials will take about 4 months to finish and make sure that the whole system will function collectively earlier than opening to passengers.
- Public Security Recommendation
- BMRCL has issued public security recommendation to maintain the general public away from sure areas of the testing websites. The protection of commuters is BMRCL’s precedence throughout this testing part.
- CRS Inspection – Final Clearance
- On completion of trials, BMRCL will submit the hall for an inspection by the Commissioner of Railway Security (CRS) – a requirement for clearance earlier than opening the road and can be utilized by the general public.
Timeline and Price range
- Preliminary Deadline & Delay Method
- Initially anticipated to be completed in 2020, the Pink Line has now been pushed again to 2026 as a consequence of unexpected delays within the course of.
- The opening will embody two phases:
- Part 1 (Elevated: Kalena Agrahara – Tavarekere): by March 2026
- Part 2 (Underground: Dairy Circle – Nagawara): between September-December 2026
Causes for the Delay
- Tunnels are all the time onerous and complicated (granite and dolerite).
- COVID-19 Pandemic: labour points and provide chain points
- Steady delay within the contractors work within the early interval.
- Delay in supply of rolling inventory.
Price range Inflation
Total, the price of Namma Metro Part II is significantly extra now than it was earlier than. The associated fee was initially quoted at ₹26,405 crore however is now ₹40,614 crore, reflecting the scale and complexity of the present work.

12 months | Occasion / Milestone | Value (₹ crore) | Remarks |
---|---|---|---|
2014 | Govt. of India authorized Part II | ₹26,405.14 crore | Preliminary Detailed Undertaking Report (DPR) estimate |
2017 | Karnataka authorized subordinate debt for land acquisition | +₹6,293.16 crore | For the revised land acquisition value |
2018–2022 | Escalation as a consequence of building delays, inflation, and many others. | (Value rising progressively) | No official cap but; underneath evaluate |
Pre-2025 | Up to date baseline earlier than Cupboard revision | ₹30,695.12 crore | Acknowledged because the official Part II estimate earlier than Might 2025 |
Might 2025 | Karnataka Cupboard authorized a value hike | +₹9,729.90 crore | Permitted improve to fulfill building value escalation |
Might 2025 | Closing Permitted Price range (Put up-Hike) | ₹40,425 crore | Official revised finances for Namma Metro Part II |
Projections | Broader estimated whole by businesses & analysts | ~₹40,614 crore | Might embody overheads, depot upgrades, signalling integration, and contingencies |
Rolling Inventory & Practice Operations
- BEML as Rolling Inventory Provider
- BEML, as a trusted Indian PSU, is finalising the order for rolling inventory for the Pink Line. 138 coaches (23 trains) have been ordered for part II, and there can be 96 coaches for the Pink Line.
- Trains’ superior options
- Some degree of driving automation
- Fireplace detection and fireplace suppression
- Tunnel air flow and strain management for passenger consolation
- Prototype and Deployment Timeline
- Prototype Supply: September 2025
- Trial operations: Late in 2025, following methods testing
- Full deployment – scheduled for March 2026
- These trains are supposed to present operational effectivity and security to the hall.
Advantages & City Influence
- Projected Ridership & Commuter Profit
- On completion, it’s estimated that the Pink Line will present service to 3-4 lakhs of passengers daily. It’s anticipated to alleviate journey time, whereas additionally offering a big quantity of individuals capability to highway transport.
- Route Entry to Key Places
- The road may have direct metro entry to the next main establishments and industrial areas in Bangalore:
- IIM Bangalore, Jayadeva Hospital, MG Highway, Shivajinagar
- Decongesting Roads and Visitors Inside the Metropolis
- Metropolis roads, similar to Bannerghatta Highway, Outer Ring Highway (ORR) and Central Enterprise District (CBD) of town will profit from much less highway site visitors.
- Multi-modal Amenities & City Improvement
- The Pink Line will permit for seamless transitional motion through BMTC, Indian Railway and different metro strains. It must also create goodwill for actual property growth, via enhanced entry to establishments, actual property and financial development alongside the hall.
Conclusion
The Namma Metro Pink Line is destined to be a landmark city transit in Bengaluru’s city transit journey. The road is on the closing milestones: security evaluation, automobile integration and CRS approval; it’s properly on its method to opening in phases by the tip of 2026. Upon opening, the road can be one of the crucial superior and vital metro corridors in India, offering secure, sustainable and seamless mobility for lakhs of Bangaloreans daily.